bogus, counterfeit, fake, false, illegitimate, sham, unreal
400%
e.g:-
l = 5 b = 2
Area= l*b =10
New after 100% increament
l=10 b = 4
Area = 10*4
No of men employed = N
No of days to finish the work = 9 days
No of men after increase = (N + 10)
No of days to finish the work = 6 days
Equating mandays
9N = (N+10)*6
9N — 6N = 60
3N = 60
N = 20
No of men employed = 20
20
(b) 16.66%
Earlier for ₹x we could purchase y gm of sugar.
Now we pay ₹1.2x for y gm of sugar
(As there was an increase in price so, x + 20%x = 1.2x)
At current rates for ₹x you can purchase y/1.2 gm of sugar
So the reduced consumption is y-(y/1.2)
Percentage change = (reduced consumption/ original consumption ) *100
That is (0.2/1.2) *100 = 16.66% (approx)
20000
Percentage of people passed = (passed in eng) + (passed in math) – ( passed in both)
Which is 90% of students passed and 10% failed
10% of X = 40
X = 400
as i assume the time taken to complete the job is not to be
changed while increasing the employees as it does not
clearly states so……….
30 men wrk for 9 hrs
therefore for the work to be done if no of workers is
increases the no of hrs / day to work should decrease so
here s a inverse relation
solving further we get
30 = K /9 ==> K= 270
now
40 = 270/y ==> y= 6.75
therefore ans is d)none
Answer is 45
First we need to subtract those reminders from the respective numbers, then we have to find the hcf of two numbers(numbers got from the subtraction) then you will get the answer.
So,
After subtraction you will get
3026-11 = 3015
5053-13 = 5040
HCF of these two numbers
5 | 3015 5040
3 | 603 1008
3 | 201 336
| 67 112
We can’t find a common diviser since 67 is a prime number
So the HCF = 5 * 3 * 3
= 45
5*3*3 = 45
9000
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
9936
C
20km