a:37
b:22
c:50
d:11
e:25
f:27
.
9
Because 2 daughter should have same age
Days taken by A to complete whole work= 140 days
Days taken by B to complete whole work= 105 days
A’s 1 day work= 1/140
B’s 1 day work= 1/105
On adding these together we get: 1/60 (1 day work by working together)
So, together they will be able to complete it in 60 days
Here is the solution to the given version of the puzzle (9 balls, one is heavier, need to identify oddball), where we label the balls A, B, …, I:
1. Weigh ABC versus DEF.
Scenario a: If these (1) balance, then we know the oddball is one of G, H, I.
2. Weigh G versus H.
Scenario a.i: If these (2) balance, the oddball is I.
Scenario a.ii: If these (2) do not balance, the heavier one is the oddball.
Scenario b: If these (1) do not balance, then the oddball is on the heavier side. For simplicity, assume the ABC side is heavier, so the oddball is one of A, B, C.
2. Weigh A versus B.
Scenario b.i: If these (2) balance, the oddball is C.
Scenario b.ii: If these (2) do not balance, the heavier one is the oddball.
answer is maximum of 2.
number1*number2=lcm*hcf
so,
product of two numbers is ,
2025=lcm*15
lcm=2025/15
lcm=135
divide 100 by 7, and you get 14.28. (Obviously you aren’t talking about decimals here) and so 14 numbers can be divisible by 7 up to 100.
The answer is 14.
A
15km/hr
4
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
7/5 * 5/q = 7/10
35/5q = 7/10
q=10