10%
time = distance / speed
speed = 36*(5/18) m/s=10m/s
distance = 100m
time=100/10s = 10sec
i improve my skills and i see u r company feed back it all are good with your company so i can join ur company
3, 8, 15, 24, 34, 48, 63
8-3 = 5
15-8 = 7
24-15 = 9
34-24 = 10 this one should be 35-24 = 11
48 – 34 = 14 based on the correction will be 48-35 = 13
63-48 = 15
the difference will create a series 5,7,9,11,13,15…..etc
Servlets are the Java programs that run on the Java-enabled web server or application server. They are used to handle the request obtained from the webserver, process the request, produce the response, then send the response back to the webserver.
3630
Let ‘x’ be the number of perons in the group and let ‘y’ be
amount per head which they have to pay.
Then xy = 2400.
or y = 2400/x
Since two friends have forget the purse, x-2 persons should
share the total amount(2400).
If they share, they have to make an extra contribution of
Rs 100 to pay up the bill
That is x-2 persons should pay y+100 each
or (x-2)(y+100) = 2400
or y+100 = 2400/(x-2)
or y = 2400/(x-2) – 100
Therefore we have got two equations namely,
y= 2400/x and y = 2400/(x-2) – 100
Comparing these two, we get
2400/x = 2400/(x-2) – 100
Solving this we get
x^2 – 2x -48 = 0
or (x-8) (x+6) = 0
or x = 8 or x = -6
Since ‘x’ denote the number of persons, it should be
positive.
So, x = 8.
32
P’s one min work=1/18
Q’s one min work=1/24
P’s x min work+Q’s 12 min work = tank fully filled ( 1 )
x(1/18)+12(1/24)=1
x=9 min
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
around 29.8
37