Can someone confirm that it is : 5/9 * 4/8 * 3/7 = 11.9% that you choose 3 good bulbs in a row
Train speed 90 km /h
1st we have to change in m/s. then 90*5/18=25m/s
Then d=speed*time
=25*10=250m train length
C. Monday
A year has 52 weeks and every week has 7 days.
We just add up one day to the present day of the year and that would automatically act as the day of the next year.
In case of leap years in between, one extra day gets added in the entire year making it 366 days instead of 365 days in an ordinary year and we add two days in that case.
1/x=1/5+1/10+1/30=lcm is 30.
->30/5=6
->30/10=3
->30/30=1
1/x=6+3+1=10
1/x=10/30=1/3=x=3
Ans is 3 hr.
8 is the answer
b’coz no two have the same age
8+6+5+4+3=26
Product of two numbers = 1320
HCF = 6
LCM = x
Formula:
Product of two numbers =(HCF *LCM)
1320=(6*x)
x=1320/6
x=220
LCM Of the numbers is220
It’s choice A because you take the last to letters and move them to the front then the previous two letters go after them and so on.
A=P+SI——(1)
sum of money after 30 years = Double the money
A=2P———-(2)
Equate 1 and 2
P+SI=2P
SI=2P-P
SI=P————-(3)
WKT, SI= PTR/100
Equate 3 and SI
P=PTR/100
P=P*30*R/100
R=P*100/P*30
R=100/30 or 10/3 or 3(1/3) %
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
D
divide 100 by 7, and you get 14.28. (Obviously you aren’t talking about decimals here) and so 14 numbers can be divisible by 7 up to 100.
The answer is 14.