It’s choice A because you take the last to letters and move them to the front then the previous two letters go after them and so on.
I think speed of printing per minute has nothing do to with how long printer being at work.
If “given day” = 8 hours.
8h = 480m
x = 176400 / 480 = 367.5 lines per minute.
A
7:8
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
3000
2 Leap years
+2 to tuedsay
Thursday is the correct answer
NON
as i assume the time taken to complete the job is not to be
changed while increasing the employees as it does not
clearly states so……….
30 men wrk for 9 hrs
therefore for the work to be done if no of workers is
increases the no of hrs / day to work should decrease so
here s a inverse relation
solving further we get
30 = K /9 ==> K= 270
now
40 = 270/y ==> y= 6.75
therefore ans is d)none
9
343 : 729 :: 125 : ?
7^3 : 9^3 :: 5^3:7^3
B. 3 : 2
Reduction of 40% or 4/10th in price of bananas will lead to an increase of 4/(10 – 4) = 2/3rd part in quantity if expenditure is constant.
If original quantity is q, then :
2q/3 = 64
=> q = 64 x 3/2 = 96 = 8 dozens.
=> Original price per dozen = 40/8 = Rs 5
3 groups
c
Monday
7days for a week so 62÷7 remainder is 6 so
After Tuesday + 6days = monday