E non of those
27 root 3
0237
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
% error= (new no-actual no)/actual no *100
% error= [(x/7)-7x]/7x * 100
% error= 48x/49x * 100
% error= 0.9795*100=97.95
x/y =5/7…………………………..(1)
(x-25)/(y-25)=35/39
59x=35y+600
dividing b.t.s by y and substituting (x/y) value from equation (1)
y=84
Now, substitue y value in equation (1)
x = 60
240 m
8/15 left.
1/15 * 4 + 1/20 * 4 = 7/15
1 – 7/15 = 8/15
3×8=24=2xt ===> t=12hours
(x+2)^2 -x^2 = 84
X=20
So (20,22)
Sum= 42
choosing my career path
Train speed 90 km /h
1st we have to change in m/s. then 90*5/18=25m/s
Then d=speed*time
=25*10=250m train length