6
c
When none of the digits are repeated:
The hundred’s place can be filled by any of the digits: 2, 3, 5, 6, 7 or 8 except the one which has already been used at the thousand’s place, so it can be filled in 5 ways.
Similarly tens’ place can be filled in 4 ways: only those 4 numbers which have not been use either at hundred’s or thousand’s place.
Unit’s place can be filled in only 3 ways. So, total number of nos. Possible =4×5×4×3= 240
6 pairs of earrings. So 12 earrings.
The total has to be 26, so let’s say there’s 6 pairs of earrings and the number of pairs has to be 4 less than the number of rings. So that would make 10 rings. The 10 rings has to be 2 1/2 greater than the number of pins. So you would divide 10/2.5 = 4 Pins. That would equate to a total of 12 earrings, 10 rings, and 4 pins. A total of 26 pieces.
789, 645, 545, 481, 440, 429, 425
b
Y
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
sorry this question is irrelevant.
1200 meter
Answer is 274 .
Let the required term be x.
Pattern :- 1) Find the difference between consecutive terms as :
2 – 1 = 1
4 – 2 = 2
13 – 4 = 9
31 – 13 = 18
112 – 31 = 81
2) Now write the above numbers obtained by differences in series as :
1, 2, 9, 18, 81, y
(Suppose y be next term after 81.)
3) Look the difference series carefully and it follows the below pattern as :
(9 * 2)/1 = 18
(18 * 9)/2 = 81
(81 * 18)/9 = 162 = y (the next term after 81)
Thus the required answer is :
x = 112 + y
x = 112 +162 =274
Lets assume total LCM(5,8) = 40units.
As, 5 men or 8 women do equal amount of work in a day,
1 Man does 8units/day and 1 Woman does 5units/day.
3M and 5W in 10 days do (3*8 + 5*5)*10 = 490units
To do 490 units in 14 days, number of Women required = 490/(14*5) = 7