Ans =18
Explanation:
Assume that initial there were 3*X bullets.
So they got X bullets each after division.
All of them shot 4 bullets. So now they have (X – 4)
bullets each.
But it is given that,after they shot 4 bullets each, total
number of bullets remaining is equal to the bullets each
had after division i.e. X
Therefore, the equation is
3 * (X – 4) = X
3 * X – 12 = X
2 * X = 12
X = 6
Therefore the total bullets before division is = 3 * X = 18
It’s choice A because you take the last to letters and move them to the front then the previous two letters go after them and so on.
47.5
1*2=2
2*2=4
2*4=8
8*4=32
Ans : 32
20&130
30/100*142.85 = approx. 100
so ans is 42.85
To solve this problem, we can break it down into steps:
Step 1: Determine the individual rates of work for A, B, and C.
If A needs 8 days to finish the task, then their work rate is 1/8 of the task per day.
If B needs 12 days to finish the task, then their work rate is 1/12 of the task per day.
If C needs 16 days to finish the task, then their work rate is 1/16 of the task per day.
Step 2: Calculate the combined work rate of A and B.
If A works for 2 days, their contribution will be 2 * (1/8) = 1/4 of the task completed.
If B works until 25% of the job is left for C, then they will complete 75% of the task.
Step 3: Calculate the time it takes for B to complete 75% of the task.
Since B’s work rate is 1/12 of the task per day, it will take B (75%)/(1/12) = 9 days to complete 75% of the task.
Step 4: Calculate the remaining work for C.
If B completes 75% of the task, then the remaining work for C is 100% – 75% = 25% of the task.
Step 5: Calculate the time it takes for C to complete the remaining work.
Since C’s work rate is 1/16 of the task per day, it will take C (25%)/(1/16) = 4 days to complete the remaining 25% of the task.
Step 6: Calculate the total time required.
A worked for 2 days, B worked for 9 days, and C worked for 4 days, totaling 2 + 9 + 4 = 15 days.
Therefore, it will take a total of 15 days for A to work for 2 days, B to work until 25% of the job is left, and C to complete the remaining work.
around 29.8
How will you know the odd is in lighter one or heavier one from only one weighing. It will require 2 weighing to find the odd set and one weighing for odd coin in that set i.e total 3 weighings.